SISS is delivered in seven milestones from April 2026 through June 2027. Dates come from docs/SISS - Project Planning V1.0 - Project Milestone.csv.

Roadmap

gantt
  title SISS M1–M7 delivery
  dateFormat YYYY-MM-DD
  axisFormat %b %Y

  section Planning
  M1 Planning & Mobilisation      :m1, 2026-04-01, 2026-04-16

  section Build
  M2 KM Digital Backbone          :m2, after m1, 2026-08-14
  M3 Technical Comment AI         :m3, after m2, 2026-10-13
  M4 BIM Visual Inspection        :m4, after m3, 2026-12-12
  M5 BIM Extraction AI            :m5, after m4, 2027-02-10

  section Acceptance
  M6 SIT / UAT                    :m6, after m5, 2027-03-12
  M7 Go-Live & Handover           :m7, after m6, 2027-06-10

Delivery schedule

# Milestone Delivery date Payment Deliverable artifact
M1 Planning & Mobilisation 2026-04-16 20% Signed initialisation doc
M2 KM Digital Backbone 2026-08-14 25% UAT / SIT sign-off
M3 Technical Comment AI 2026-10-13 15% UAT / SIT sign-off
M4 BIM Visual Inspection 2026-12-12 15% UAT / SIT sign-off
M5 BIM Extraction AI 2027-02-10 15% UAT / SIT sign-off
M6 SIT and UAT completion 2027-03-12 5% Certificate of System Acceptance
M7 Go-Live and Final Handover 2027-06-10 5% Project Closure Report

Architecture increment per milestone

Each milestone adds a well-defined slice of the platform. The services exist as deployable skeletons from M2 onward; each later milestone activates their features.

Milestone Architecture increment
M2 core-svc, submission-svc, workflow-svc, comment-svc (basic), ai-svc (compliance extraction + HITL), notification-svc, signing-svc (interim trust). SPA with PSP + officer consoles, submission dashboard
M3 comment-svc full (inline markup, library, revision compare, response tracker), ai-svc comment drafting + risk highlight, advanced dashboard, SLA monitor
M4 bim-svc validation + tile pipeline, xeokit viewer in SPA, operational dashboards
M5 bim-svc metadata extraction + zoning comparison, exceedance flagging, federated-view mode
M6 Security and performance hardening, VAPT, load testing, final CA trust-anchor cutover
M7 Production promotion, hypercare, runbooks, training

Release gates

Every milestone has a set of acceptance criteria that must pass before the next begins. See Release gates for the full list per milestone.

Current execution focus

The approved implementation plan targets M2 (14 August 2026). Teams should already leave clean extension points for M3–M5 in every service they touch.

See M2 plan for the execution breakdown.